SONG Chenghui, LI Wei, JIANG Fuqiang, REN Wenfeng, LI Shouding. COMPARISON AND SELECTION OF ENGINEERING GEOLOGY AND ROUTES ACROSS EAST AFRICAN RIFT VALLEY—TAKE THE NAIROBI-MALABAR RAILWAY FOR EXAMPLE[J]. JOURNAL OF MECHANICAL ENGINEERING, 2020, 28(1): 141-148. doi: 10.13544/j.cnki.jeg.2019-287
Citation: SONG Chenghui, LI Wei, JIANG Fuqiang, REN Wenfeng, LI Shouding. COMPARISON AND SELECTION OF ENGINEERING GEOLOGY AND ROUTES ACROSS EAST AFRICAN RIFT VALLEY—TAKE THE NAIROBI-MALABAR RAILWAY FOR EXAMPLE[J]. JOURNAL OF MECHANICAL ENGINEERING, 2020, 28(1): 141-148. doi: 10.13544/j.cnki.jeg.2019-287

COMPARISON AND SELECTION OF ENGINEERING GEOLOGY AND ROUTES ACROSS EAST AFRICAN RIFT VALLEY—TAKE THE NAIROBI-MALABAR RAILWAY FOR EXAMPLE

doi: 10.13544/j.cnki.jeg.2019-287
Funds:

the CCCC Major Basic Research and Development Projects 2017-ZJKJ-08

the National Science and Technology Major Project 2016ZX05034-003

  • Received Date: 03 Jul 2019
  • Rev Recd Date: 21 Nov 2019
  • Publish Date: 25 Feb 2020
  • The Nairobi-Malabar railway project is an important part of the "northern corridor" of East Africa. It is the trunk line of economic development in landlocked African countries. The railway line works pass through the rift valley. The volcanic landform, the fault belt and the tension fracture are extremely development. However, there is a lack of research data on railway construction in the rift valley. To study railway lines through the rift valley, firstly, this paper introduces the topography, landform, development mechanism and regional fault distribution of the east African rift valley, and then formulates three major railway routes through the east African rift valley based on the economic control points along the railway. We had compared the terrain and landform traversed by the three major routes, the stratum, fault and ground fractures, the earthquake and volcanic developments, and the adverse geological disasters. Finally, the investment, advantages and disadvantages of each route had been compared, and finally the southern route scheme was recommended. The scheme of the route was approved and adopted by the Kenyan government. At present, the Nairobi Malaba railway is in trial operation, and the practice shows that the selection of the rift section of Nairobi-Malabar railway is relatively successful, which can provide reference for similar projects.

     

  • loading
  • Baker B H, Wohlenberg J. 1971. Structure and evolution of the Kenya rift valley[J]. Nature, 229(5286): 538-542. doi: 10.1038/229538a0
    Chorowicz J. 2005. The East African rift system[J]. Journal of African Earth Science, 43(1-3): 379-410. doi: 10.1016/j.jafrearsci.2005.07.019
    Ebinger C J. 1989. Tectonic development of the western branch of the East African rift system[J]. Geological Society of America Bulletin, 101(7): 885-903. doi: 10.1130/0016-7606(1989)101<0885:TDOTWB>2.3.CO;2
    Feng M H. 2007. Construction and engineering geology siting for the Qinghai-Tibet railwayfeng[J]. Journal of Engineering Geology, 15(SII): 33-37.
    Gregory J W. 1986. The great rift valley[M]. London: John Murray: 422.
    He Z N. 1987. Preliminary discussion on the problem of railway line selection in active fault zone[J]. Journal of Railway Engineering Society, (3): 195-203.
    Kampunzu A B, Popoff M. 1991. Distribution of the main phanerozoic African Rifts and associated magmatism: Introductory notes[C]//Magmatism in Extensional Structural Settings. Berlin Heidelberg: Springer: 2-10.
    Li G H. 2004. Wu-Guang railway line selecting by geology in Da-Yaou Mountain district[J]. Railway Investigation and Surveying, 30 (6): 33-34, 37. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=tlhc200406011
    Li J C. 2009. Engineering geological route selection of Qinghai-Tibet railway[M]. Lanzhou: Lanzhou University Press.
    Li X J, Zhou Z H, et al. 2016. Seismic hazard analysis report for the CK0-CK120 section of the Nairobi-Malaba Railway in Kenya[R]. Beijing: Institute of Crustal Stress, China Earthquake Administration, Institute of Geophysics, China Earthquake Administration, Nanjing University of Technology.
    Morley C K. 1989. Extension detachments and sedimentation in continental rifts(particular reference to East Africa)[J]. Tectonics, 8(6): 1175-1192. doi: 10.1029/TC008i006p01175
    Qian J, Liu H J, Yu Q H, et al. 2009. Permafrost engineering geological characteristic and discussion of route selection in Qinghai-Tibet plateau[J]. Journal of Engineering Geology, 17(4): 508-515. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=gcdzxb200904012
    Ring U. 2014. The East African fift system[J]. Austrian Journal of Earth Sciences, 107(1): 132-146.
    Wen Z X, Tong X G, Zhang G Y, et al. 2012. Petroleum geology features and exploration potential of basin group in east African rift system[J]. China Petroleum Exploration, (4): 60-65.
    Xu Z L, Li G H, Xu Z Y, et al. 2002. Assessment of regional crust stability of south Shandong province and site selection for Jiaoxin railway[j]. Journal of Engineering Geology, 10(2): 210-215. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=gcdzxb200202019
    Yu X D. 2018. Route selection by engineering geological in east Africa rift valley section of the railway from Nairobi to Malaba in Kenya[J]. Railway Investigation and Surveying, (4): 113-116.
    Zhang J M, Feng X. 2019. A comparative study on routing of nairobi-Malabar railway in Kenya[J]. Railway Freight Transport, (3): 54-58. http://d.old.wanfangdata.com.cn/Periodical/tdhy201903011
    Zhou L Z. 2018. Application of geological route selection in the south extension line of hummer railway[J]. Gansu Technology, 34(16): 84-85.
    Zielke O, Strecker M R. 2009. Recurrence of large earthquakes in magmatic continental rifts: insights from a paleoseismic study along the laikipia-marmanet fault, Subukia Valley, Kenya Rift[J]. Bulletin of the Seismological Society of America, 99(1): 61-70. doi: 10.1785/0120080015
    丰明海. 2007.青藏铁路建设与工程地质选线[J].工程地质学报, 15(SII): 33-37. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=HY000002769719
    何振宁. 1987.活动断裂带铁路选线问题初探[J].铁道工程学报, (3): 195-203. http://d.old.wanfangdata.com.cn/Conference/291830
    李光辉. 2004.新建武广铁路大瑶山区地质选线[J].铁道勘察, 30(6): 33-37. doi: 10.3969/j.issn.1672-7479.2004.06.011
    李金城. 2009.青藏铁路工程地质选线[M].兰州:兰州大学出版社.
    李小军, 周正华, 等. 2016.肯尼亚内罗毕—马拉巴铁路CK0-CK120段地震危险性分析报告[R].北京: 中国地震局地壳应力研究所, 中国地震局地球物理研究所, 南京工业大学.
    钱进, 刘厚健, 俞祁浩, 等. 2009.青藏高原冻土工程地质特性与选线原则探讨[J].工程地质学报, 17(4): 508-515. doi: 10.3969/j.issn.1004-9665.2009.04.012
    温志新, 童晓光, 张光亚, 等. 2012.东非裂谷系盆地群石油地质特征及勘探潜力[J].中国石油勘探, (4): 60-65. doi: 10.3969/j.issn.1672-7703.2012.04.010
    许再良, 李国和, 许兆义, 等. 2002.鲁南地区区域地壳稳定性评价与胶新铁路地质选线[J].工程地质学报, 10(2): 210-215. doi: 10.3969/j.issn.1004-9665.2002.02.019
    俞晓东. 2018.肯尼亚内马铁路东非大裂谷段工程地质选线[J].铁道勘察, (4): 113-116. http://d.old.wanfangdata.com.cn/Periodical/tlhc201804028
    张健明, 冯旭. 2019.肯尼亚内罗毕至马拉巴铁路通道研究[J].铁道货运, (3): 54-58. http://d.old.wanfangdata.com.cn/Periodical/tdhy201903011
    周志立. 2018.地质选线在瓮马铁路南延伸线中的应用[J].甘肃科技, 34 (16): 84-85. doi: 10.3969/j.issn.1000-0952.2018.16.030
  • 加载中

Catalog

    Figures(11)  / Tables(1)

    Article Metrics

    Article views(224) PDF downloads(0) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return